The
The first renovation project occurred during 1999-2000, which converted the upper 8 floors of the building to a telecommunications lease building. Our design services included:
- Design of fire protection sprinkler system renovations for the building, including removal of the existing gravity storage tanks on the 14th floor and design of a new electric fire pump at the lowest level of the building. New sprinkler stairwell risers were installed throughout the building while maintaining existing active sprinkler systems on the lower floors.
- Design of new domestic water booster pump system.
- Conversion of the 11th floor to an 11kv transformer substation room with electrical shafts incorporated into the building for telecommunication and power tenant distribution risers. This floor was also planned for approximately 30 telecommunication tenant emergency generator layouts and we were responsible for designing generator ventilation and engine exhaust systems for the floor within the limited constraints of the building.
- A new diesel storage fuel tank facility was designed in the
The second renovation project occurred during 2007-2008, which converted the Basement level, 1st floor and 2nd floor of the building (approximately 163,000 sq. ft.) to office lease space. Our design services included:
- Design of a new central system water-source heat pump loop for the floors by utilizing an existing 800-ton cooling tower on the 12th floor roof and existing condenser water main risers routed through the historical building. New condenser water pumps and plate-and-frame heat exchangers were installed in the Basement with new variable speed heat pump loop pumps and piping distributed to the floors for tenant connection to provide air conditioning throughout the year.
- Design of a new hot water fin tube radiation heating system, which involved removal of all existing steam heating systems on the floors, installation of new steam-hot water heat exchangers and new hot water heating pumps, piping and perimeter fin tube to the floors.
- New ventilation systems were incorporated into the building by installing 100% outside air and relief air handling units in the Basement below the adjacent
- Design of new domestic water risers, sanitary/vent risers and condensate wet column risers in discrete locations for tenant connection.
- Design of new energy management and tenant electrical metering systems.
- Full power distribution system design for the tenant and mechanical spaces was included. This involved modifications to 11th floor substations and busduct routings to multiple floors for flexible power distribution.
- Fire alarm and telecommunication system extensions were provided for each new tenant floor.
- Design of a new centralized lighting control system to enable time schedule based control of public and landlord space lighting.
The third and most recent renovation project is currently under construction (2008-2009). It is similar in nature to the second renovation project and involves the conversion of 6th, 8th and 9th floors of the building (approximately 222,000 sq. ft.) to office lease space. Our design services included:
- Design of a new central system water-source heat pump loop for the floors, including removal of an existing cooling tower and supporting steel structure on the 12th floor roof and the installation of a new 1000-ton cooling tower on new steel framing. New mechanical systems have been designed on the 11th floor, including condenser water pumps, plate-and-frame heat exchangers, variable speed heat pump loop pumps and piping distributed to the floors.
- Design of a new hot water fin tube radiation heating system, which involved removal of all existing steam heating systems on the floors, installation of new electric hot water generators on the 11th floor and new hot water heating pumps, piping and perimeter fin tube to the floors. All mechanical equipment on the 11th floor has been installed on raised structural support framing with spring-type inertia base equipment pads because of the limited floor loading capacity of the floor and to reduce vibration transmission into the existing structure.
- New ventilation systems were incorporated into the building by installing 100% outside air and relief air handling units on the 14th floor of the building, which previously housed large sprinkler and domestic water gravity storage tanks. The air handling units have been carefully designed and are sectionalized to permit rigging from
- Ventilation and relief air risers have been provided from the units through central utility shafts for tenant connection
- Design of new domestic water risers, sanitary/vent risers and condensate wet column risers in discrete locations for tenant connection.
- Design of new energy management and tenant electrical metering systems.
- Additional busduct power distribution was designed for the new tenant floors.
- Fire alarm, telecommunication and lighting control systems were extended to new tenant floor.
- This project has been submitted to the USGBC for LEED Gold rating under Existing Building Core and Shell.
